[ROHA] Update on new sewer pump.

  • From: Isaac Moore Jr <isaacmoore2@xxxxxxxxxxx>
  • To: roha list <roha@xxxxxxxxxxxxx>
  • Date: Tue, 21 Mar 2023 17:17:17 +0000

Hello,

I stop by and spoke to the construction manager whose crew is working on the 
new Sewer pump construction, along Park Forrest.

1.  They are replacing all of the old plumbing and also upgrading to 6 inch 
piping from 4 inches.

2.  They expect the entire work to continue for an additional 3 to 4 weeks.

3.  Once completed, they will erect an 8 feet, chain linked, enclosed fence 
around everything.

4.  I will continue to watch their progress, also ensuring they correct any 
damages that might occur by their parking on the grassy areas.